Belle Meade Plaza Redevelopment
Construction Updates
Belle Meade Village is a cosmopolitan shopping and residential village at the gateway to Belle Meade, Tennessee. Set for completion in 2028, Belle Meade Village will transform an underutilized 15.5-acre site into an iconic shopping and residential village, creating an irreplaceable destination at the entrance to Nashville’s most established residential corridor.
Green space, public walkways, and parks will comprise approximately 60% percent of the project site, including the activation of Richland Creek and connection to its namesake greenway, connecting residents to the pedestrian-friendly Sylvan Park neighborhood and McCabe Park.
Construction Updates
Fall 2025
October: Project mobilization and construction commenced.
November: Excavation and blasting began on November 12th. The blasting phase is expected to last approximately 12 weeks, with 2-3 blasts per day scheduled at 9:00 a.m., 11:00 a.m., and 1:00 p.m., and an additional 3:00 p.m. slot reserved as a possible extra blast time.
Please Note: Blast times are approximate and may vary slightly throughout the day. For the safety of pedestrians and motorists, traffic will be stopped at the intersection of Harding Pike and White Bridge Rd. approximately 5 minutes before and after scheduled blast times.
Winter 2025/2026
December: Deep foundations and crane installations begin.